Case Study-Church Retrofit Project
St Andrew’ Presbyterian Church - 115 St . Andrews Road Scarborough
Supply and install 2 square 4” 20ft poles in the parking lot, One pole is completed with receptacle at 2ft down from top of pole. Poles to be feed from the existing circuit and wiring on site. 2. Supply and install 2 concrete bases for the pole mounted fixtures. Pole bases will be installed in the same location of the exiting poles, remove the exiting wood poles. Supply and Install 2 flood lights with 1 bullhorn on the wall and power via existing circuit at 25ft 5. Supply and install 1 flood light on the west side of wall at 25ft (relocate the light) 7 photocells build-in with 7 new light fixtures.